Project Location: Battle Mountain, Nevada

Client: Newmont USA

Synopsis of work:

A new leach pad construction for this copper facility measured approximately 9,000,000 square feet. It contains solution collection channels and ponds on the south side. Ames built a haul road from the mine, installed culverts and piping, constructed a secondary containment channel and placed clay liner on edge berms, ponds, collection channels, and leak detection channels over compacted sub-grade.

The clay was topped with a synthetic liner and covered with a fine protective layer, produced by Ames’ aggregate crushing operation.

Click to enlarge any of the photos below:

Leach pad construction contains solution collection channels and ponds
Constructed a secondary containment channel, collection channels and leak detection channels
Clay liner was topped with a synthetic liner and covered with a protective layer