Synopsis of work:

While most copper mines experienced dwindling ore grades and reserves, the Morenci mine in Southwestern United States has increased its copper production with the discovery of a large primary sulfide deposit below its existing operations.

Ames crews constructed an ore stockpile facility over the top of a previous stockpile, spanning 500 acres. More than 50 pieces of equipment were on site to excavate and haul rock materials.

In addition to earthwork, the project included construction of power line roads and foundations, foundations for two primary power stations, two HDPE solution ponds and a haul road. The work scope integrated crushing and placement of material over liner, and installing 1.4 million linear feet of piping. Construction of three miles of overland conveyor corridors required extremely tight tolerances for positioning the conveyor.

Click to enlarge any of the photos below:

Built two HDPE solution ponds, crushed and placed material over liner and installed 1.4 million linear feet of piping
An ore stockpile facility was constructed over the top of a previous stockpile, spanning 500 acres
Power line roads and foundations were constructed for two power stations and three miles of conveyor corridors