Faraday Repower

Faraday-main
Faraday-24
Faraday-19
Faraday-project-168
Faraday-people-19
Faraday-project-71
Faraday-project-132

Ames crews worked under a tight schedule to complete construction of the Faraday hydroelectric plant on the Clackamas River in northwestern Oregon.

The plant replaces the original powerhouse dating to 1907. Joining the project after the demolition of the original structure and several years into construction of the new facility, Ames built suspended decks, elevated walls, retaining structures, a pump station, and thrust restraints. The work included wall pours up to 65 feet above the generator floor elevation.

The Pacific Northwest climate posed a challenge to the project’s already compact schedule. When Ames took over the project, three large, elevated decks needed to be placed to start other work activities. The large, flat pours required hard trowel finishing and were difficult to schedule during the rainy winter months. The crew worked diligently to protect and heat these pours to maintain the schedule and allow other subcontractors to start their work.

As the project continued, the scope increased, but crews adapted to meet the original schedule. Ames also worked with the client to redesign several aspects of the project to keep it moving forward for on-time completion.

On Jan. 31, 2023, the new Faraday Powerhouse began generating emissions-free hydropower. The modernization effort improved efficiency, reliability, and operational safety. The state-of-the-art structure is designed for seismic safety and produces more consistent power regardless of river flows. In addition, the highly efficient turbines are safer for juvenile fish migrating to the ocean.

Following plant commissioning, Ames continued performing site improvements including drainage structures, light foundations, and a penstock thrust block.

Markets: Hydroelectric

Location: Estacada, Oregon

Completed: July 2023

Services:

  • Structural concrete

Details:

  • Wall pours 65 feet above the generator floor