Ames was a joint venture partner for the 36-mile RTD Eagle P3 (Public-Private Partnership) design-build project, the first mass transit P3 project of this magnitude in the United States.

The contract included construction of 36 miles of new double-track electric commuter rail lines, 14 miles of new freight rail track work, 32 bridges, 30 at-grade crossings, 14 stations with Park-n-Ride lots, and a major vehicle maintenance facility. The project scope included grading, concrete, and structures work.

The Eagle P3 is comprised of RTD’s East Rail Line, Gold Line, Commuter Rail Maintenance Facility, and Northwest Rail Line Westminster segment. The commuter rail lines opened one at a time in sequence through 2016.

Markets: Railroad, Transportation, Mass Transit

Location: Denver, Colorado

Client: Regional Transportation District (RTD)

Completion: July 2016

Delivery: P3 (Public-Private Partnership) Design-Build

Services:

  • Grading
  • Structural concrete

Details:

  • 1.3 million cubic yards of earthwork
  • 1 million square feet of retaining walls
  • Nearly 1,000 utility conflict relocations

Star Performance Status

Voluntary Protection Program, OSHA

Star companies have achieved injury and illness rates at or below the industry national average and demonstrate an exemplary worksite with comprehensive, successful safety and health management systems.